City Power technicians

City Power technicians were robbed at gunpoint. Photo: City Power/ Facebook.

City Power promises to intensify efforts to curb ongoing power outages

City Power spokesperson Isaac Mangena said the outages have been plaguing northern Joburg due to various factors…

City Power technicians

City Power technicians were robbed at gunpoint. Photo: City Power/ Facebook.

City Power says it has taken proactive measures to address the ongoing power outages affecting Northriding, Olivedale, and the surrounding areas.

CITY POWER SHARES PLANS TO REDUCE POWER OUTAGES


As this has become a source of frustration for residents, the municipal power utility has shared that it has intensified efforts to rectify the situation.

City Power spokesperson Isaac Mangena said the outages have been plaguing northern Joburg due to various factors, including equipment failure, vandalism, theft, and cable faults.

“We understand the residents’ frustration about not having a power supply for extended periods. City Power has been hard at work to restore the power supply for all residents as soon as possible,” said Mangena.

ALSO READ: City Power threatens to cut off Joburg hospitals owing millions

THE SEQUENCE OF EVENTS

The recent issues began on Saturday, 30 September when the Olivedale area began experiencing low voltage. Eskom operators were initially dispatched to investigate, but they could not identify the fault. The matter was then referred to City Power, according to Mangena.

  • On Sunday, 1 October, City Power operators discovered an open circuit, and efforts were made to resolve the low voltage problem, including ordering necessary materials for repairs. Challenges arose during repairs, as the cable was situated in a difficult location, crossing bushes and a river.
  • On Tuesday, 3 October, the repairs were completed; however, the cable failed tests upon restoration. The testing team struggled to locate the fault on the same day. A breakthrough occurred on Wednesday, 4 October when a stolen cable was found, and the fault was identified. Repairs continued throughout the night and were completed by Thursday, 5 October.

ALSO READ: PAY UP! Joburg inner city customers owing City Power R2.5 billion

“Final tests were conducted, and the power supply was restored by midday. A permanent solution to reroute the cables from vulnerable areas such as bushes and rivers was implemented, offering a more secure infrastructure that is less prone to theft and vandalism. This project was successfully concluded on Monday, 9 October.”

Mangena

ALSO READCity Power: Questions to ASK suspicious workers and contractors on site

MANGENA RELAYS MORE POWER DISRUPTIONS IN THE NORTH

He added that for Northriding, recurring outages began after a third party mistakenly damaged a City Power cable during their project. 

“The challenging nature of working in a water-logged area with multiple service cables resulted in frequent power supply interruptions. Delays were further exacerbated when the entity was slow to respond to requests to drain the water from the trench, making it unsafe for teams to work with electricity,” he explained.

ALSO READCity Power prohibits digging during LOADSHEDDING to curb vandalism

On Tuesday, 10 October, a phase fault triggered another outage.

“Efforts are ongoing to implement a long-term, permanent solution, which has proven challenging due to infrastructure constraints in the area. Additional teams from different Service Delivery Centres have been deployed to expedite repairs,” Mangena assured.

READ MORE ARTICLES BY SISO NAILE